Rossford's mayor says a proposed data center must meet his "non-negotiables" before it moves forward

The Daily Toledo teamFrom Wednesday’s edition · 1 min read · 2 sources

ShareEmailFacebookX

If you live near Rossford's , a data center is on the table. , a Florida-based developer, has submitted a site plan, and Mayor Neil MacKinnon III calls it a "micro" data center at about 90,000 square feet. Meta's data center in Middleton Township is nearly eight times that size.

Rossford's proposed data center is far smaller than Meta's

Floor area of the proposed data center, beside places you know

The proposed data center90,000 sq. ft.About 10 megawatts
Meta's Middleton Township data center715,000 sq. ft.Being built
A football field57,600 sq. ft.end zones included
A basketball court4,700 sq. ft.NBA size

19 basketball courts would fit inside the proposed data center

Source: BG Falcon Media

View as table
Floor area
The proposed data center90,000 sq. ft. (About 10 megawatts)
Meta's Middleton Township data center715,000 sq. ft. (Being built)
A football field57,600 sq. ft. (end zones included)
A basketball court4,700 sq. ft. (NBA size)

“It can't raise utility rates. It can't be loud. It can't ruin air quality. It can't ruin water quality.”

Mayor Neil MacKinnon III, on the city's "non-negotiables"

Neighbors have questions. Joyce Theisen, whose home would be next to the site, is just learning about the plans and worries about traffic and noise. Richard Avalos, 49, says residents have "less of a say in things as time goes on."

  • Next: QLevr presents at a public Planning Commission meeting
  • Then: City Council, likely three meetings before a vote
  • Zoning: site is already planned industrial, no change needed

Want to weigh in? WTVG reported residents can attend a zoning meeting on Nov. 11, which is today. We'd confirm the time and place with the city first.

The Rossford data center plan by the numbers

10 megawatts
is about the proposed data center's power, per the mayor
3 meetings
is how long City Council would likely take before a vote
Nov. 11
is the zoning meeting residents can attend

Sources: BG Falcon Media, WTVG

Read it in the full edition

More from Wednesday’s edition

Read the edition
All city hall news
  1. WTVG2 hours ago

    Lucas County commissioners approve next steps for jail renovation plans, on WTVG

    Navarre said in a statement Tuesday that he hopes commissioners will permit the SSOE team to consider a direct supervision design, which he believes would be safer and require fewer personnel.

  2. Sent-trib6 hours ago

    Perrysburg Twp. approves series of repairs to buildings, equipment, on Sent-trib

    PERRYSBURG – When it rains is pours and such is the case at Perrysburg Township with the trustees authorizing repairs to buildings and equipment.

  3. WTOL11 hours ago

    Toledo's proposed budget could mean fewer workers and services, on WTOL

    The plan calls for 89 layoffs, cuts to nuisance mowing and blight crews, and the elimination of a recycling center.